Abnahme is not just getting the keys: defects checks for a new-build apartment
Abnahme of a new-build flat in Germany is a legal step, not a key handover. What it changes, unit vs common property, and a defects checklist.

Overview
When you buy a new-build apartment from a developer (Bauträger), acceptance (Abnahme) is a legal declaration that the work is essentially as contracted. The keys only give you possession. Acceptance starts the five-year limitation period for defect claims, shifts the burden of proof onto you and can cost you rights over defects you saw but did not reserve. Treat the appointment as a contract step: bring an independent construction expert (Bausachverständiger), record and reserve every defect in writing, and remember that the common property (Gemeinschaftseigentum) is accepted separately from your own unit.
For the administrative side of taking over (meters, service charge, documents), see the handover checklist.
Abnahme vs handover: what acceptance changes
A developer contract combines construction with a land purchase. Work-contract law governs the construction and sales law the transfer of the land (§ 650u(1) BGB). That is why a new build has an Abnahme at all.
| Until acceptance | From acceptance | Source | |
|---|---|---|---|
| Limitation of defect claims | Not running | Five years for a building, counted from acceptance | § 634a(1) no. 2, (2) BGB |
| Burden of proof | The developer must prove the work is free of defects | You must prove a defect, except for defects you reserved | § 363 BGB; BGH, VII ZR 64/07, para. 15 |
| Defects you knew of | Rights unaffected | Rights to remedy, self-remedy, withdrawal and price reduction lost unless reserved. Damages are not on that list, but reserve every known defect anyway | § 640(3), § 634 BGB |
| Contractual penalty for late completion, if agreed | Claimable as agreed | Claimable only if reserved at acceptance | § 341(3) BGB |
| Risk of accidental damage | Developer | You | § 644(1) BGB |
| Payment | Instalments as construction progresses | The price is due on acceptance; a developer contract follows its MaBV instalment plan (see below) | § 641(1) BGB; § 3(2) MaBV |
Acceptance can happen without a signature. If the developer sets a reasonable deadline after completion and you neither accept nor refuse by naming at least one defect, the apartment counts as accepted. For a consumer, this applies only if the developer warned of that consequence in text form with the request (§ 640(2) BGB). A private individual buying one apartment to let is generally a consumer (§ 13 BGB); check with your lawyer if you buy through a company.
Conduct counts too. The Federal Court of Justice (BGH) has confirmed that taking a building into use can amount to implied acceptance, depending on the circumstances (BGH, 12 May 2016, VII ZR 171/15, para. 52). Moving a tenant in is not a neutral act.
You may not refuse acceptance because of insignificant defects (§ 640(1) BGB). For those, accept with reservations. None of this replaces a lawyer's reading of your contract, which may set its own acceptance procedure.
Private unit and common property: two acceptances
A condominium apartment combines your unit (Sondereigentum) with a share in the common property: the land and every part of the building not in separate ownership (§ 1(2), (5) WEG). Parts needed for the building's structure or safety are common property even inside your apartment (§ 5(2) WEG): the roof, façade, load-bearing walls and shared pipes. Windows and the balcony door are usually treated the same way. The declaration of division (Teilungserklärung) shows the allocation.
Each buyer accepts both. The BGH treats every buyer as the client for the common property too, entitled to decide on its acceptance personally, with expert advice if wanted, or through a trusted person of their choosing (VII ZR 171/15, para. 45). Your unit is usually inspected at handover; the common property often months later, once the building and outdoor areas are finished.
Read the acceptance clauses before signing and again before handover. The BGH has held these standard clauses invalid:
- acceptance of the common property by a first administrator (Erstverwalter) the developer can appoint, because of the risk that such an administrator will not check neutrally (BGH, 12 September 2013, VII ZR 308/12), including a subsidiary of the developer (BGH, 9 November 2023, VII ZR 241/22);
- binding later buyers to an acceptance an engineering firm had declared before they signed, which also shortened their limitation period indirectly (VII ZR 171/15).
The Stuttgart Higher Regional Court has also held invalid a clause handing acceptance to a sworn expert to be elected by the owners' meeting (OLG Stuttgart, 6 June 2024, 13 U 419/19). Where such a clause fails, the common property may never have been validly accepted, so the limitation period may not have started, and the developer cannot rely on the missing acceptance to resist defect claims (VII ZR 241/22). That protection arrives through litigation, years later. Better to take part in the common-property acceptance, yourself or through an expert you appoint, and ask your lawyer whether to revoke any acceptance power of attorney in the contract.
Why bring an independent Bausachverständiger
The developer's site manager leads the walk-through and writes the record. You need someone on your side who can recognise a defect, judge whether it is significant and describe it precisely. Choose an expert with no link to the developer. Publicly appointed experts are sworn to work independently and impartially (§ 36(1) GewO) and are listed in the chambers' expert directory (SVV, German). Buyers in one building often hire a single expert for the common property, each authorising them individually.
A defect is measured against the contract: the work must have the agreed quality (§ 633(2) BGB). Your expert therefore needs the notarised contract, the building description (Baubeschreibung), plans and any agreed extras (Sonderwünsche); see what a building description includes.
Alpha Minoris's Buyer's Agent service can coordinate the acceptance appointment for purchases in Berlin, Dresden or Leipzig: agreeing the date with the developer, sending your expert the contract, specification and plans, and filing the signed record and photographs. You need not live in the city. It does not carry out a technical inspection; that is the expert's job, and the legal assessment is your lawyer's. Its mandate runs until the keys, so a common-property acceptance months later needs its own arrangement.
New build Abnahme checklist: before, during and after
Before the appointment
| Task | Why |
|---|---|
| Read the acceptance clauses for unit and common property with your lawyer | Spot clauses handing acceptance to the developer's administrator or expert; decide on any power of attorney |
| Book an independent Bausachverständiger | The developer's staff run the inspection |
| Collect contract, building description, plans, agreed extras, change correspondence | A defect is a deviation from the agreed quality |
| Check the invitation: date, deadline, text-form warning | Silence after a proper deadline can count as acceptance |
| Note any agreed penalty for late completion | It must be reserved at acceptance |
| Ask which instalments fall due at handover and completion; tell your lender | Plan any withholding with your lawyer before the day |
| Pack: phone with timestamps, torch, spirit level, floor plan, numbered defect sheet | Evidence you can reproduce later |
During the appointment
| Task | Why |
|---|---|
| Go room by room with the expert, including balcony, cellar compartment and parking space | Nothing missed because it is outside the flat |
| Test windows, doors, shutters, taps, drains, heating, ventilation, sockets, intercom | Function, not just appearance |
| Record each defect: location, description, photo reference, reserved | The reservation must be made at acceptance |
| Mark defects in common property seen from the unit | They go to the common-property acceptance as well |
| List keys, manuals, meter readings and documents handed over | Completeness of the handover |
| Do not sign "free of defects" or any waiver; add your own remarks if the record is incomplete | Your signature confirms the record |
| Leave with a copy signed by both sides | Proof of every reservation |
After the appointment
| Task | Why |
|---|---|
| Send the defect list with remedy deadlines in writing | Starts the follow-up and documents it |
| Re-inspect each remedy with the expert | Sign off only what is fixed |
| Pay or withhold only as agreed with your lawyer; instruct your lender | An unjustified deduction can put you in default |
| Check the terms of the 5 per cent completion security before it is returned (§ 650m(2) BGB, applied by § 1 AbschlagsV) | It secures completion without significant defects |
| Diary both five-year end dates and an inspection before them | Claims are time-limited |
| Attend the common-property acceptance or appoint an expert | Your own right and decision |
| File the record, photos and letters | Evidence, and records for your tax adviser |
Defect record template
Illustrative example. Fictional figures. Apartment B: Leipzig, 50 m², bought off-plan from a developer for €250,000; contract notarised Thursday 6 March 2025. The contractual completion date is 1 November 2026, a Sunday, when possession, benefits and burdens pass. The developer's letter of Friday 16 October 2026 invites the buyer to the unit acceptance on Friday 30 October 2026 and includes the text-form warning. Cost estimates are the buyer's expert's; the remedy deadline is four weeks.
| No. | Location | Description | Photo ref. | Unit or common property | Reserved | Remedy deadline | Expert's estimate |
|---|---|---|---|---|---|---|---|
| 1 | Living room, by balcony door | Parquet dented and scratched, about 10 cm | B-01 to B-03 | Unit | Yes | 27 November 2026 | €600 |
| 2 | Living room, balcony door | Does not close tightly; draught at lower seal | B-04, video V-01 | Probably common property (façade) | Yes | 27 November 2026 | €350 |
| 3 | Bathroom, shower tray | Silicone joint missing along the wall | B-05 | Unit | Yes | 27 November 2026 | €150 |
| 4 | Cellar compartment 7 | Damp patch on outer wall, about 40 × 60 cm | B-06, B-07 | Probably common property | Yes; cause to be investigated | Investigation by 27 November 2026 | Not estimated |
The unit is accepted on 30 October 2026 with all four reservations. Items 2 and 4 are recorded now to preserve the evidence and raised again at the common-property acceptance.
Reservations, refusal and withholding
Reserve. Every visible defect goes on the record as reserved, signed by both sides, plus any agreed penalty for late completion.
Refuse only for significant defects. If you refuse, naming defects, the developer can ask for a joint record of the apartment's condition; if you miss that appointment without good reason, it can make the record alone. Once you have the apartment, an obvious defect missing from the record is presumed to have arisen later and to be your responsibility, unless it cannot have been caused by you (§ 650g BGB).
Withhold with advice. Where you can demand that a defect be put right, you may refuse an appropriate part of a payment that has fallen due, normally twice the remedy cost (§ 641(3) BGB). For items 1 and 3 in the example, that is 2 × €750 = €1,500. This is a statutory benchmark, not an instruction: agree any deduction with your lawyer, including whether common-property defects justify one.
Know which instalments remain. Under the Real Estate Agents and Developers Ordinance (MaBV), the remaining 70 per cent of the price after the first instalment is split into stage shares of that remainder, including 12 per cent after readiness for occupation in exchange for possession, 3 per cent for the façade and 5 per cent after full completion (§ 3(2) MaBV). For Apartment B, that is €21,000, €5,250 and €8,750. Our new-build comparison groups the first two (€26,250) at handover; the last follows full completion, assumed in March 2027. These are payment stages, not acceptance. See Bauträger payment plans.
Follow-up after acceptance
- Set deadlines in writing (here, Friday 27 November 2026) and ask for appointments.
- Check remedies with your expert before signing anything off.
- Escalate through your lawyer if deadlines pass. Self-remedy, price reduction and damages each have their own conditions (§ 634 BGB).
- Diary the end dates. The unit's five years end with 30 October 2031. If the common property is accepted on Monday 1 March 2027, its period ends with 1 March 2032 (§ 634a BGB; § 187(1), § 188(2) BGB). Book an expert inspection about six months before the first date. For a fraudulently concealed defect, the regular period applies, never ending before the five years.
- Report common-property defects to the administrator and follow the owners' meetings. In the 2023 BGH case, the owners' association pursued the claims on the buyers' behalf (VII ZR 241/22).
If the developer's finances worry you, the questions in assessing the developer apply here too.
Once the apartment is let, Vermieter-Autopilot can follow up defects inside the unit within the agreed mandate, arranging tenant access for the developer's contractors and chasing appointments. The claims stay with you and your lawyer.
Frequently asked questions
Can I refuse to accept a new-build apartment?
Only for significant defects. Accept insignificant ones with a written reservation. If you refuse, name the defects in writing and expect a joint condition record.
What happens if I ignore the developer's request to accept?
If the developer set a reasonable deadline after completion and warned you of the consequences in text form, the apartment counts as accepted once the deadline passes without a refusal naming at least one defect.
Does letting the apartment count as acceptance?
It can. Taking a building into use may be implied acceptance, depending on the circumstances. Complete the formal acceptance, with a written record, before the tenant moves in.
Who accepts the common property?
Each buyer, personally or through someone they appoint. The BGH has held invalid standard clauses handing that decision to an administrator the developer can appoint.
Next step
Before your acceptance date, line up the contract, the building description and an independent expert. Discuss your first rental property with Alpha Minoris.
Sources and references
Accessed 4 October 2026.
- § 650u BGB, developer contract: work-contract law for construction, sales law for the land (para. 1); excluded provisions (para. 2): Open source
- § 640 BGB, duty to accept; no refusal for insignificant defects (para. 1); deemed acceptance after a reasonable deadline unless refused naming at least one defect; consumer warning in text form (para. 2); loss of § 634 nos. 1 to 3 rights for known, unreserved defects (para. 3): Open source
- § 634 BGB, buyer's rights for defects (remedy, self-remedy, withdrawal or price reduction, damages): Open source
- § 634a BGB, five years for a building (para. 1 no. 2), from acceptance (para. 2), fraudulent concealment (para. 3): Open source
- § 633 BGB, para. 2, freedom from defects means the agreed quality: Open source
- § 641 BGB, payment due on acceptance (para. 1); withholding an appropriate part, as a rule twice the remedy cost (para. 3): Open source
- § 650g BGB, joint or unilateral condition record after refusal; presumption for obvious defects not recorded: Open source
- § 363 BGB, burden of proof after acceptance as performance: Open source
- BGH, judgment of 23 October 2008, VII ZR 64/07 (NJW 2009, 360): contractor bears the burden of proving freedom from defects before acceptance (headnote a); no reversal for defects reserved at acceptance, because § 363 BGB requires acceptance as performance (para. 15). Full text on the LMU teaching site of Prof. Stephan Lorenz: Open source
- § 341 BGB, para. 3, contractual penalty must be reserved on accepting performance: Open source
- § 644 BGB, para. 1, risk passes on acceptance: Open source
- § 13 BGB, consumer definition: Open source
- §§ 187(1), 188(2) BGB, computing periods that start with an event: Open source and Open source
- § 650m BGB, para. 2, 5% security for timely completion without significant defects: Open source
- § 1 AbschlagsV (Verordnung über Abschlagszahlungen bei Bauträgerverträgen), developer instalments under § 3(2) MaBV; § 650m(2) and (3) BGB apply: Open source
- § 3 MaBV (S9), para. 2: 30% after earthworks begin; of the remainder, 12% after readiness for occupation and in exchange for possession, 3% for façade works, 5% after full completion: Open source
- §§ 1(2), 1(5) and 5(2) WEG, unit, common property, structural parts as mandatory common property: Open source and Open source
- BGH, judgment of 12 May 2016, VII ZR 171/15 (BGHZ 210, 206): each buyer is the client for the common property and may decide on acceptance personally or through a trusted person (para. 45); clause binding later buyers to an earlier acceptance invalid (paras. 44 to 47) and an indirect shortening of limitation (paras. 49, 50); implied acceptance by taking into use depends on the circumstances (para. 52). Official text: Open source
- BGH, order of 12 September 2013, VII ZR 308/12: standard clause allowing acceptance of the common property by a first administrator the developer can appoint is invalid under § 307(1) BGB (headnote; paras. 6 to 10, risk that the administrator does not check neutrally). Official text: Open source
- BGH, judgment of 9 November 2023, VII ZR 241/22: clause allowing acceptance by an economically linked (subsidiary) first administrator invalid; developer as user of the clause may not rely on the missing acceptance when the owners' association pursues common-property defect claims for the buyers (headnotes). Official text: Open source
- OLG Stuttgart, judgment of 6 June 2024, 13 U 419/19, as reported by the German Notary Institute (DNotI): clause on acceptance by a sworn expert elected by the owners' meeting invalid under § 9(1) AGBG (old law); limitation begins only with acceptance; no forfeiture in the developer's favour: Open source
- § 36 GewO, para. 1, publicly appointed experts sworn to independence and impartiality: Open source
- DIHK, IHK-Sachverständigenverzeichnis (SVV), about 8,000 publicly appointed and sworn experts from chambers of commerce, architects, engineers and agriculture: Open source
- Alpha Minoris service scope: owner-supplied definitions in the brief update (Buyer's Agent, preparation to keys; Vermieter-Autopilot, ongoing ownership; Berlin, Dresden and Leipzig).
Explore selected rental properties
See the numbers, compare options, and book a conversation from any property.
View all selected properties →